Corridor 11 of 12
Comberton Greenway
The programme's flagship — England's first cycle street at one end, and the biggest surviving new off-road route at the other.
Under construction
What became of the 8 proposals for this corridor
What the 2016 review asked for
- Widen the Coton to M11 bridge path, 400 m, and repair the bridge surface
- New ramps and path from the M11 bridge into West Cambridge, 300 m
- Replace the Bin Brook bridge on Burrell's Walk
- A safe crossing of Long Road, assumed to be a new underpass
- New path on field edges and bridleway, Coton via Hardwick to Comberton Village College, 5 km
What happened
- Spring 2019Initial consultation.
- 25 June 2020Board approves the route at £9m.
- July 2022Camcycle consultation guide; Long Road is to get a parallel crossing, not an underpass.
- December 2022Executive Board approval to proceed.
- 29 September 2025Construction starts in Coton village.
- 13 October 2025Adams Road works begin — England's first Cycle Street, carrying around 3,000 cyclists a day.
- 5 March 2026Full business case approved, together with the Sidgwick Avenue experimental traffic order.
- 2026Planning application submitted for the full route, Comberton to central Cambridge.
- August 2026Adams Road complete.
- Early 2026Coton village complete, with a 20mph limit following later in the year.
Where it stands, September 2026
Part open, part in planning. The Cambridge end — Adams Road, Grange Road, Coton village — is finished. The rural 5 km from Coton through Hardwick to Comberton Village College, the largest new off-road route left in the whole programme, is in the planning application. The review's assumed grade-separated Long Road crossing has become a surface parallel crossing; the review had argued that at peak times 'a safe crossing is important' and that a concrete box could be installed relatively quickly.
Every proposal on this route
| Proposed intervention (2016) | Type | Scale | Status 2026 | What happened |
|---|---|---|---|---|
| Widen and upgrade the path and ramps from the edge of Coton to the M11 bridge | Upgrade | 400 m | In design or planning | In the planning application submitted in 2026. |
| Repair the surface of the bridge over the M11 | Upgrade | 1 bridge | In design or planning | In the scheme. |
| New ramps and path from the M11 bridge into the West Cambridge site at Charles Babbage Road | New route | 300 m | In design or planning | In the scheme — the link the review called it 'surprising' to have gone without. |
| Remove the low wall at the Adams Road / Wilberforce Road junction | Upgrade | — | Built and open | Adams Road, England's first cycle street, was completed in August 2026. |
| Replace the Bin Brook bridge on Burrell's Walk with a wider one | New structure | new bridge | In design or planning | Still in the scheme, unbuilt. |
| Safe crossing of Long Road between Coton and Comberton — assumed to be a new underpass | New structure | underpass | Delivered differently | The 2016 report assumed a grade-separated crossing, noting a concrete box could be installed quickly. The scheme now proposes a surface parallel crossing. |
| New path on field edges and bridleway from Coton via Hardwick to Comberton Village College | New route | 5 km | In design or planning | The largest surviving new off-road route in the programme; included in the 2026 planning application. |
| Investigate extending the route to Cambourne, the Eversdens, Barton and Bourn | New route | various | Not in current programme | Not progressed. |